| Project Number |
Job |
Owner |
General Contractor |
Architect |
Percent Completed |
Scheduled Completion |
Contract Amount |
| 101 |
Meadowbrook High School |
Chesterfield County |
Siemens Building Technologies |
Siemens Building Technologies |
68% |
August-02 |
$137,970.00 |
| 114 |
Capital One - Campus Service Building |
Capital One |
Century Construction Co. |
Simmons, Rockecharle & Prince |
99% |
June-02 |
$735,853.00 |
| 117 |
Little Sisters of the Poor |
same |
KBS, Inc. |
Rawlings & Wilson |
99% |
June-02 |
$617,027.00 |
| 119 |
The Virginia Home |
same |
Bovis Lend Lease |
Baskervill & Son |
59% |
August-02 |
$798,185.84 |
| 123 |
Bowe Street Parking Deck |
Virginia Commonwealth University |
Kenbridge Construction Co. |
HSMM |
73% |
September-02 |
$430,502.00 |
| 125 |
KPMG - James Center |
Two James Center Assoc. |
Century Construction Co. |
The M Group |
89% |
June-02 |
$167,199.24 |
| 201 |
Federal Prison Elevator |
Federal Government |
RCI, Inc. |
Bailey Associates Architects |
0% |
June-02 |
$14,995.00 |
| 202 |
Grayland Baptist Church |
same |
J. M. Bell |
The Depasquale Gentilhomme Group |
0% |
August-02 |
$87,695.00 |
| 203 |
Brown's Island Lighting |
Downtown Presents |
n/a |
Baskervill and Son |
62% |
June-02 |
$101,830.00 |
| 205 |
Maury School |
City of Richmond |
Pinnacle Construction Co. |
HS Engineering |
0% |
September-02 |
$368,460.00 |
| 206 |
Lewis Ginter Botanical Gardens Conservatory |
same |
Kjellstrom & Lee |
The Glave Firm |
5% |
September-02 |
$227,335.41 |
| 207 |
Mary Washington Fitness Center |
Mary Washington College |
Haley Builders |
Marcellus, Wright, Cox & Smith Architects |
0% |
June-03 |
$194,390.00 |
| 208 |
West Point Auditorium |
|
|
|
0% |
December-02 |
$504,455.00 |
| 209 |
Calhoun Community Center |
City of Richmond |
Johnson Controls |
Johnson Controls |
42% |
September-02 |
$13,850.00 |
| |
Total: $4,399,747.49 |
|